Home awaits new pool project. (Ready)

Home awaits new pool project. (Ready)

Scraping Sod to be removed and hauled away. (Day 1)

Scraping Sod to be removed and hauled away. (Day 1)

Laying Out Pool! (Day 2)

Laying Out Pool! (Day 2)

Excavation of pool and hauling dirt.   (Day 3 & 4 )

Excavation of pool and hauling dirt. (Day 3 & 4 )

Graveling bottom of pool.  (Day 5)

Graveling bottom of pool. (Day 5)

Steeling pool with Steeltex and rebar.  ( Day 6)

Steeling pool with Steeltex and rebar. ( Day 6)

More Steeltex, rebar and Drain Plumbing .  (Day 7 )

More Steeltex, rebar and Drain Plumbing . (Day 7 )

Finishing up steel rebar and steeltex .  ( Day 8 )

Finishing up steel rebar and steeltex . ( Day 8 )

Final Steel Rebar should look like this without the infloor cleaning system .  (Day  9 )

Final Steel Rebar should look like this without the infloor cleaning system . (Day 9 )

Building Inspector checks steel rebar construction for approval.  ( Day 10)

Building Inspector checks steel rebar construction for approval. ( Day 10)

Gunite Concrete Crew Starts (Day 11 )

Gunite Concrete Crew Starts (Day 11 )

Gunite Concrete Crew Starts Shooting Pool Shell. (Still Day 11 )

Gunite Concrete Crew Starts Shooting Pool Shell. (Still Day 11 )

Gunite Concrete Crew Carving Pool Shell. (Still Day 11 )

Gunite Concrete Crew Carving Pool Shell. (Still Day 11 )

Gunite Concrete Crew Completes Pool Shell. ( Still Day 11 )

Gunite Concrete Crew Completes Pool Shell. ( Still Day 11 )

Pool plumbing crew digs ditches and pipes pool. ( Day 12 )

Pool plumbing crew digs ditches and pipes pool. ( Day 12 )

Plumbers Finishes Plumbing and Setting Pool Equipment.. ( Day 13 )

Plumbers Finishes Plumbing and Setting Pool Equipment.. ( Day 13 )

Underground Plumbing Inspection Approval (Day 14 )

Underground Plumbing Inspection Approval (Day 14 )

Plumbing backfill is complete and tile crew starts (Day 15 )

Plumbing backfill is complete and tile crew starts (Day 15 )

Electrician hooks up lights and equipment for power. (Day 16 )

Electrician hooks up lights and equipment for power. (Day 16 )

Coping forms or paver coping is placed and deck is formed. (Day 17 )

Coping forms or paver coping is placed and deck is formed. (Day 17 )

Inspections on deck forms, elevation, drainage for approval. (Day 18

Inspections on deck forms, elevation, drainage for approval. (Day 18

Deck is poured or pavers installed. (Day 19 )

Deck is poured or pavers installed. (Day 19 )

Deck is textured for nonslip. (Day 20 )

Deck is textured for nonslip. (Day 20 )

Deck is Painted with industrial Acrylic Paint. (Day 21 )

Deck is Painted with industrial Acrylic Paint. (Day 21 )

Screen crew arrives for installation if there is a screen. (Day 22 )

Screen crew arrives for installation if there is a screen. (Day 22 )

Screen is completed and ready for Interior. ( Day 23 )

Screen is completed and ready for Interior. ( Day 23 )

Interior finish crew arrives for application. ( Day 24 )

Interior finish crew arrives for application. ( Day 24 )

Interior finish is complete and water is filling pool! ( Day 25 )

Interior finish is complete and water is filling pool! ( Day 25 )

Child safety fence is installed or door and window alarms. ( Day26 )

Child safety fence is installed or door and window alarms. ( Day26 )

Starting pool equipment and adding chemicals. ( Day 27 )

Starting pool equipment and adding chemicals. ( Day 27 )

Completing sod and landscaping . ( Day 28 )

Completing sod and landscaping . ( Day 28 )

Pool Is complete and ready to swim!  ( Day 29 )

Pool Is complete and ready to swim! ( Day 29 )

Don't forget to call for Final inspection! ( Day 30 )

Don't forget to call for Final inspection! ( Day 30 )